Hostel Construction Update: Steady Progress Despite Early Delays

We’re grateful to share an update on progress with the hostel construction project. While the build has not been without challenges, encouraging progress is being made and momentum is now building as we move into a critical phase of the schedule.

Early Delays and How We Responded

As with many construction projects, we experienced several early delays. These included additional site clearance work that became necessary once construction began, as well as a prolonged Christmas and New Year shutdown period in South Africa, which affected manufacturing and supply timelines.

Recognising the risk of knock‑on delays, we took decisive steps to adjust procurement and sequencing, helping us regain valuable time later in the programme.

Excellent Work on the Ground

We are especially thankful for the work of the bricklayers, who have progressed quickly and delivered a high standard of workmanship throughout. We also want to acknowledge Goodson’s attentive supervision, together with the care and diligence shown by the foremen on site. Their commitment has been a real encouragement and has contributed significantly to the quality and pace of the build.

Construction Progress to Date

  • West Dormitory: Construction is now complete up to roof height, marking a major milestone.
  • Toilet and Shower Block: Additional building work is still required. Progress here is temporarily paused while we await delivery of structural steel from South Africa.
  • East Dormitory: To avoid further delays, we decided to bring forward procurement for this block. If all goes to plan, we may be able to complete it in time for the upcoming conference.
  • Common Room: The floor slab for the common room and East Dormitory are ready for construction to begin

February Procurement Trip to South Africa

In February, Stephen and Goodson, together with Gail and Anna, made a productive procurement trip to South Africa. This allowed us to source materials directly, ensure quality, and reduce the risk of future supply interruptions.

From South Africa, we are purchasing:

  • Roofing sheets and structural steel
  • Plumbing materials and sanitaryware for 10 showers and 10 toilets
  • Electrical wiring, lighting, ceiling fans, and accessories
  • 36 internal doors
  • Almost 90 aluminium windows
  • Steel to construct bunk beds
  • Paint and finishing materials

Materials in Transit

The first truck‑load of materials is currently at the Malawi border customs post, and we are praying for a smooth and timely clearance process. A second truck‑load is scheduled to depart in approximately two weeks, which will enable roofing and internal works to progress in parallel.

Solar, Water, and Utilities

We are sourcing solar PV panels, batteries, inverters, and solar hot‑water geysers from a highly reputable supplier in Malawi. The company is run by a brother in the Lord whom we trust implicitly, and this local partnership also helps ensure reliable after‑sales support.

In addition, foundation work has begun for a 40,000‑litre water storage tank, a critical component for reliable water supply once the hostel is operational.

A Tight but Achievable Schedule

The coming weeks are crucial. We are now working to a very tight schedule to complete roofing and internal works so that the hostel will be usable by the end of May. While there is still much to do, we are encouraged by the progress so far and thankful for the Lord’s provision at each stage.

Please continue to pray for:

  • Timely customs clearance at the border
  • Safe transport of materials
  • Strength and wisdom for those overseeing the work
  • Favour as we work towards completion

Thanks

We want to express our sincere thanks to all who have supported this project through prayer and financial giving. This hostel is only possible because of the faithfulness and generosity of God’s people, many of whom will never see the building in person but have invested sacrificially in the work. Your prayers sustain those overseeing the project, and your gifts have enabled us to move forward with confidence at each stage. We are deeply grateful for your partnership in this work and for sharing in the vision of providing safe, functional accommodation to support the ministry.

We look forward to sharing further updates as the project continues.